Courtland Lodge- Phase two
Former British Legion Club Courtland Rd Paignton.
December 2016
Remove all ground floors, demolish non supporting block walls – dig footings for new party walls stages required due to supporting walls.
December 2016
Resin – rebar and mesh to new footings of external walls - Reinforcing bar on chairs – concrete foundations.
December 2016
Removal of concrete stairway and associated walls to landings - supporting of floor & cross tie steels.
January 2017
Under build party walls to new dpc height & concrete oversite.
January 2017
Removal of external support wall for opening to new kitchen - extension to be built – System 160 used to support floors & walls – make door opening from lounge to new patio.
Febuary 2017
Ground floor joists hung between party walls & temporary build on decking with new kitchen extension under construction.
Febuary 2017
Party walls built to new 1st floor height with laid new floors & removal of existing joists & floors cut out cross tie steels.
March 2017
Party walls built to new 2nd floor height & new floors laid to support gantry scaffolding for roof removal - party walls continued to ridge height.
March 2017
Ring beam shuttered onto existing external walls for bolting down of wall plates - Lifting roof timbers & construction of new cut roof.
April 2017
Turret roof supported whilst the octagonal support frame is fitted to the bay opening.
May - July 2017
New conservatory base is built of stone & brick to match existing – stairs fitted - roofs & internal walls insulated.
August 2017
Windows & front doors fitted - turret bay & conservatory fitted – externals to be completed.
November 2017
Courtland Lodge completed comprising three Town houses.